Mission 1: Start-up Phase: Mission 1 will include (1) the collection and analysis of baseline data, (2) the implementation of a raw water and HIS measurement campaign, and (3) the completion of a comprehensive assessment of the existing situation. The timeframe for completing Mission 1 is 4 months.
Mission 2: APS Study. Mission 2 consists of carrying out an APS including the study of three (3) rehabilitation variances.
Mission 3: Preliminary Design Study: detailed study of the option selected at the preliminary design stage with a level of detail allowing for the development of a "Shopping List" type tender document. The completion time for Mission 3 is 6 months.
Mission 4: EIA: In parallel with the completion of Missions 2 and 3, the BIC will conduct an environmental and social impact assessment of the rehabilitation work for the selected option. This study will include standard elements such as public consultation, EIA, and ESMP, as well as a hazard and ATEX study of the selected option, in accordance with Tunisian regulations.