  • Location: Cities of Bambari and Bozoum
  • Duration of the mission: 06 months (studies) and 18 months (work)
  • Name of the Client : MINISTRY OF ENERGY AND WATER GENERAL DIRECTORATE OF HYDRAULIC COORDINATION OF PROJECT ACTIVITIES

Drinking water supply and water resources management

UPDATE OF EXISTENT DETAILED DESIGNS, PREPARATION OF CONSTRUCTION TENDER DOCUMENTS, ASSISTANCE AND EXAMINATION OF THE EVALUATION OF BIDS AND THE PROCUREMENT OF WORKS AND CONTROL AND SUPERVISION OF WORKS FOR THE WATER SUPPLY AND SANITATION FACILITIES IN THE CITIES OF BAMBARI AND BOUZOUM


L’Objectif de la Mission est d’assister l’Unité de Coordination du Projet (UCP) dans la mise en œuvre du projet de réhabilitation et d’extension de systèmes d’approvisionnement en eau potable et d’assainissement dans les villes de Bambari et Bozoum. La prestation du Consultant consiste à : Actualiser les études d’APD disponibles à la Direction Générale de l’Hydraulique, élaborer les Dossiers d’Appel d’Offres ; assister l’UCP à la passation des marchés de travaux et assurer le contrôle et la supervision des travaux d’alimentation en eau potable et d’assainissement dans les villes de bambari et bozoum. La durée totale de la mission est répartie en 3 phases qui sont à étaler sur les trente (30) mois de durée de la phase opérationnelle du projet
Phase I : Update of studies and development of the construction tender documents (5 months).
Phase II : Support the Project Coordination Unit in the evaluation of tenders and award of works contracts (1 month).
Phase III : Control and supervision of works (18 months).


Update of the preliminary design: layout of networks and production and storage facilities; design and sizing
Preparation of detailed technical specifications of the works.
Elaboration of the descriptive plans of the works with the exact geometrical characteristics of the works.
Preparation of a support/supervision program in relation to the work execution schedule.
The preparation and implementation of a socio-economic animation program related to the works to be realized.
Preparation of a "maintenance manual" to pass upon receipt of the works to the Client and to recipients of the book, which specifies the list of maintenance tasks, their importance and eva-luation the cost of maintenance during the first 2 years after completion, task by task, as annual budgets
Preparation of tender and execution folders.
Customer support for procurement of works.
Monitoring and control of work until final acceptance.